The leaky dam at Hyatt Lake in Oregon is being shored up this summer as part of a $3.7 million seismic retrofit.
The Mail Tribune reported the project will bring the dam east of Ashland into safety compliance after a seepage issue was discovered during a 2009 inspection.
Greg Garnett of the federal Bureau of Reclamation says engineers are nearly finished with designs. Work is expected to start in mid-May and run into mid-November.
Because of the project, Hyatt Lake will be kept no higher than four feet from full pool this summer,
That’s not expected to impact the Talent Irrigation District’s ability to store and deliver irrigation water this year. It also won’t change the Oregon Department of Fish and Wildlife’s trout-stocking plans.
ODFW plans to stock 10,200 legal-sized trout there this spring and 39,000 larger fingerlings in October.
Topics Catastrophe Natural Disasters
Was this article valuable?
Here are more articles you may enjoy.
Bayer’s Supreme Court Win in Roundup Case No ‘Silver Bullet’
Mamdani Delivers Rent Freeze in Milestone for New York City Tenants
What Happens to Property Pricing in ’27, Insurance, Reinsurance Execs Ask
‘Ghost Broker’ Who Procured 1,120 Policies Through Fraud Arrested 